Image_Case Study_Centre Parcs_4

Center Parcs Woburn

In December 2004, Center Parcs announced that it had identified a location for a fifth UK site, at Warren Wood near Flitwick, Bedfordshire. Center Parcs Woburn Forest was a £250 million development, one of the largest leisure projects in the UK.

The Project

Center Parcs Woburn Forest is a £250 million development, one of the largest leisure projects in the UK.  The project includes the construction of accommodation, indoor and outdoor facilities, a sub-tropical swimming complex, restaurants and a spa.

Sector:
Leisure
Location:
Bedfordshire
Client:
ISG Plc
Value:
£250m
Product:
Timber Frame

The Challenge

Kingspan Timber Solutions was required by the main contractor, ISG plc, to produce large volumes of high quality
structures within an exacting build programme. The heavily wooded site made access difficult for lorries and
cranes, so the panels were designed to be small and light enough to be handled by four men. Construction was
to be closed fully insulated timber panels to address the thermal requirements. The commercial team planned an
accurate delivery schedule enabling ISG to synchronise with other site suppliers.

The Solution

Image_Case Study_Centre Parcs_3
Initially 625 lodges were built, with 6 spa suites, complete with a 17,000m2 lake at the centre. Kingspan Timber Solutions built a prototype lodge at its’ Bedfordshire-based factory to trial the speed and efficiency and to ensure quality.

The Kingspan site management team of 6 had early problems with snow and ice. However, working closely with ISG, they adapted the build sequence and overcame any issues to deliver the last plot by December 2013.

“The high degree of skill and expertise consistently demonstrated by the Kingspan team provided us with a great deal of confidence in the delivery of an incredibly challenging project, both in terms of scope and scale. Kingspan’s solution driven approach was an important factor in our successful relationship, and the company’s ability to plan ahead and offer us a transparent working methodology, with clearly defined processess, provided enhanced certainty in programme delivery. This made project management much more straight forward and Kingspan actively contributed to the smooth running of the programme.”


Paul Gransby, Construction Director - ISG

Download
Image_Case Study_Centre Parcs_1
Previous
Next

Find out more

Kingspan Timber Solutions Ltd

Please contact us to discuss your project

Eltisley Road

Great Gransden

Sandy

Bedfordshire

SG19 3AR

01767 676400

We use cookies on our website www.kingspan.com. To find out more about the cookies we use, or to change your cookie preferences i.e. to remove your consent to our use of certain categories of cookies, please visit our Cookie Policy & Control page.

Please click "Accept and close" to accept the use of cookies on our website. If you do not click "Accept and close" but continue to use this website: you thereby consent to the use of all Kingspan's cookies and third party cookies for the purposes of improving performance, improving functionality and audience measurement, in accordance with the terms laid out in our Cookie Policy & Control page; and we will assume that you have read and understood our Cookie Policy & Control page.

The Cookie Policy & Control and Website Privacy Notice were updated on 13 August 2018.